A quiet curving residential street bordered by native limestone and mature live oaks in West Lake Hills.

Loop 360 Now Runs Under Westlake Drive. The Local Half of the Project Is Still Unfinished.

If you head down Westlake Drive toward Loop 360 on a weekday morning, the Loop 360 mainlanes no longer stop for a signal at the bottom of the hill. A driver on Loop 360 headed for Pennybacker Bridge now stays in the left lane, passes under the Westlake Drive bridge, and keeps going without stopping. If you live on the Westlake Drive side, though, you still exit right, drive the connector road, and turn around on a bridge.

That split sums up where TxDOT's Westlake Drive/Cedar Street project stands as Thanksgiving approaches. The part built for through traffic opened at the end of summer. The parts that decide how West Lake Hills gets on and off the highway, and how anyone walks or bikes across it, are scheduled to finish last.

Through traffic got its lanes on Aug. 30

KXAN reported on Aug. 28, 2026 that TxDOT planned to open one new lane in each direction that Sunday morning, so drivers could bypass the signals at Westlake Drive and Cedar Street while the connector roads kept local access. The Austin American-Statesman's highway project tracker has a photo of traffic flowing under the Westlake and Cedar bridges on Sept. 1, 2026.

The project has been underway since June 2022. Copasa Group is the contractor, and the total cost is $72.1 million, paid for by TxDOT and the City of Austin's 2016 Mobility Bond. The finish date has slipped once. The Statesman tracker shows projected completion moving from mid-2026 to late 2026, and TxDOT's project page now says "late 2026, weather permitting."

What remains is Phase 5: final paving and striping, then the switch to permanent traffic patterns. For someone driving through, the change already happened. Most of what is still coming affects the trip that starts on Westlake Drive.

How the trip from Westlake Drive works for now

TxDOT describes the interim setup as one Loop 360 lane open in each direction, with the connector roads handling everything else. From the West Lake Hills side, it looks like this:

  1. Heading north toward Pennybacker Bridge or south toward Bee Cave Road? Either way, you start on the connector road, because the mainlanes now run below the intersection.
  2. To reach Loop 360 in either direction, use the non-signalized U-turns on the Westlake Drive bridge. TxDOT says these give access to both northbound and southbound Loop 360.
  3. Coming home on Loop 360, stay out of the left lane, which carries through traffic, and exit right for Westlake Drive or Cedar Street.
  4. Southbound and need to turn around farther north, the U-turn south of Bold Ruler Way stays open, according to the TxDOT release KXAN cited.

That Bold Ruler U-turn has some history. In TxDOT's February 2025 community Q&A, the project team said it was "currently evaluating" whether an extra U-turn south of Bold Ruler could be added safely, after residents asked for one, without "creating additional issues such as bypass traffic through neighboring communities." Today it is part of the official access instructions.

TxDOT posts overnight lane and access closures on its project page. In November, these have included overnight closures of the Westlake Drive and Cedar Street access points at Loop 360, so check the page before a late-night drive. Under the current schedule, excavation runs weekdays from 7 a.m. to 7 p.m. and Saturdays from 9 a.m. to 3 p.m., and hauling is done at night.

What changes when the permanent layout opens

Several of the awkward spots drivers have worked around since the bridges went up are temporary by design. TxDOT has said so directly in its February 2025 Q&A:

Movement Interim setup Final layout, per TxDOT
Northbound Loop 360 to Cedar Street A narrow left-lane "exit" Left-turn lanes at Cedar sit at grade and are reached from the connector roads
Right turn from Westlake Drive onto northbound Loop 360 A tight turn Called part of the temporary configuration, with the team evaluating improvements
Cedar Street U-turn lanes Temporary traffic-shift arrangement Not listed as the finished solution
Westlake Drive bridge U-turns Serve both directions Serve both directions

The bottom row matters most to West Lake Hills. In the final design, the U-turns on the Westlake Drive bridge stay as the way onto Loop 360. The turnaround you are learning this fall is the one you will keep.

The finished project will look different too. TxDOT's aesthetic plan calls for natural limestone surfaces, painted finishes, star motifs, and retaining walls treated to look like native stone.

The paths reach the highway, then stop

The project also adds walking and biking routes along and across Loop 360 at both intersections. In its February 2025 Q&A, TxDOT described them like this:

"Alongside the new mainlanes, these 10 ft wide paths are generally 5 ft away from the roadway's curbs and gutters. They will not be striped but are wide enough for bicyclists and pedestrians to use simultaneously without conflict. There will also be protected east to west shared use paths on the Westlake and Cedar Street bridges."

TxDOT lists the shared-use paths in Phase 2, which is still in progress. At the north end, TxDOT's 2019 workshop handouts showed the path connecting to Pennybacker Bridge, and a path near the Loop 360 boat ramp linking to the bike and pedestrian facilities already there. The bridge itself stays as it is. TxDOT has also said it has no plans to widen Pennybacker Bridge.

The paths run north and south along the highway, and the two bridge paths take you across it. Once you are across, heading east into West Lake Hills means Westlake Drive or Bee Cave Road. A continuous east-west route through town belongs to a different project.

The east-west route is still a study with a deadline

On Oct. 8, 2025, West Lake Hills City Council approved an interlocal agreement with the Capital Area Metropolitan Planning Organization to study a trail along or near Eanes Creek between Loop 360 and MoPac. City documents describe it as a safer, more comfortable route parallel to Bee Cave Road, Community Impact reported. The study budget is $520,000. CAMPO covers $416,000 and the city covers $104,000.

CAMPO's request for proposals defines the corridor as running from Loop 360 to MoPac at Barton Skyway, through West Lake Hills, Austin, Rollingwood, and unincorporated Travis County. It also lists recent work along the creek: the new West Lake Hills City Hall at 4010 Bee Cave Road, and the removal of the low-water crossings at Eanes Creek on Camp Craft Road and on Eanes Creek Road.

Here is where the study stands on paper:

  • Nov. 17, 2025: CAMPO issued the RFP.
  • April 13, 2026: Toole Design Group ranked first of 10 respondents with 101 of 125 points, just ahead of Nelson\Nygaard at 100 and Halff Associates at 98. CAMPO staff asked the Transportation Policy Board to authorize the executive director to negotiate and execute a contract with the top-ranked firm.
  • June 8, 2026: CAMPO's work program listed the study as "Contract TBD."
  • Sept. 30, 2027: The city-CAMPO agreement expires.

The RFP expects the study to take 12 to 18 months from work authorization. Either party can end the agreement with 30 days' written notice. Even the shortest study, started now, would run until late 2027, so the work schedule and the agreement's end date are already close together.

Residents will get a say once the study starts. The RFP requires at least three community meetings, both in person near the corridor and online. It also calls for a project website and public preference surveys at key points, plus interviews and focus groups with the Westlake Oaks HOA, Rolling Hills Home Guardians, property owners, and Eanes ISD. The study's stated goals include supporting the city's Master Plan, the City of Austin Urban Trails Plan, and the Great Springs Trail.

For now, a bike rider coming off the new path on the Westlake Drive bridge can cross Loop 360 safely, and then has the same choice of roads into town they had before construction started in 2022.

If you're keeping an eye on how Westlake Drive and Loop 360 affect your daily drive, or thinking about how changes like these show up when you sell or buy on this side of town, Ace Team ATX is happy to talk through what we're seeing street by street. Let's find your Austin home.

Work With David

By intently listening to his clients' needs, he goes above and beyond their expectations in helping them achieve their unique real estate goals. As a result, many of his clients become long-term friends.

Follow Me on Instagram