If you live in Barton Hills and drive north, you probably start the same way. You go up Azie Morton Road along the edge of Zilker Park, wait at the light, and turn onto Barton Springs Road just east of the creek crossing. The City of Austin's own 2023 council document describes that crossing as "the primary northern entrance to the Zilker and Barton Hills neighborhoods via Azie Morton Road."
The City plans to replace that bridge. Most of the public debate has been about the structure itself, a concrete arch that turned 100 this summer. The City's plans have not yet set a final layout for the Azie Morton intersection or a staging plan for keeping traffic moving during construction. Neither will be settled at the open house coming up on Monday, November 16.
A century old and still carrying the traffic
According to Community Impact, the Barton Springs Road Bridge opened June 21, 1926. It was widened on one side in 1946. In 2023 a City official told the council's Mobility Committee that about 20,000 vehicles cross it every day, both park visitors and people heading in and out of the city, as the Austin Monitor reported.
The City rates the bridge in fair condition overall. It also says the dimensions, sidewalks and bike lanes fall short of current design standards. A 2023 condition assessment led Transportation and Public Works to post signs telling large loads to use only the right lane, as a precaution to extend the bridge's life. Staff warned that if nothing changed, trucks and buses could eventually be restricted from the bridge altogether. The Monitor reported that engineers found corrosion in the reinforcing steel. At a minimum, the deck and the spans between supports would need full replacement.
In December 2023, City Council directed staff to pursue replacement. The engineering team had studied five options, from preserving the existing structure to replacing it entirely. Staff recommended a three-span bridge with "Y-shaped" piers set in line with the creek, which leaves more open space underneath for paddlers, the Ann and Roy Butler Hike and Bike Trail, and the Zilker Eagle. In November 2024 the project won a $32 million federal grant from the U.S. Department of Transportation's Bridge Investment Program, the Austin Monitor reported.
Barton Hills voices on both sides
The centennial became part of the replacement debate. On June 21, Save Our Springs Alliance held a celebration at the bridge, with swimming and tacos in the morning and live music from Bill Oliver and the Otter Space Band in the evening. The Barton Hills Neighborhood Association listed the event on its announcements page. Community Impact reported that the alliance ran a petition booth opposing the City's plan. The group argues that restoration would cost less than demolition and a wider replacement, and that construction would harm Barton Creek habitat, the adjacent Umlauf Sculpture Garden and a nearby archaeological district.
In February, ahead of a February 4 Historic Landmark Commission meeting, residents sent written comments both ways, and the comments posted to the City's records include Barton Hills residents on each side. One Barton Hills resident forwarded the Zilker Neighborhood Association's position and endorsed it. ZNA's statement reads:
"We urge the City Council to protect and preserve this bridge indefinitely and to reverse the decision to replace it with a standard highway-style bridge."
In that statement, ZNA says the estimated cost of replacement has risen from $40 million to $54.5 million, and it describes that as leaving a significant unfunded gap. ZNA proposes a separate bike and pedestrian bridge alongside the existing one instead. The most recent City figure in this research is an April 2025 council agenda item. It pairs the $32 million grant with an $8 million City match, for a project total of up to $40 million.
A Barton Hills family wrote in support of replacement. They called the bridge beautiful but "dangerously narrow for pedestrians and cyclists" and asked for protected bike lanes and wide sidewalks on both sides. They also raised the detail closest to everyday neighborhood traffic, asking the City to extend the right-turn lane on Azie Morton Road where it meets Barton Springs Road.
The City's position on the bridge's status is narrow and specific. The bridge is not a designated historic structure on its own. It counts as a contributing resource to Zilker Park, which is listed in the National Register of Historic Places, and historic resources are part of the environmental review now underway. The City also estimates that rehabilitation would cost about as much as replacement and add up to 50 years of service, while a new bridge would be expected to last at least 100.
What the current design includes
The City's project page describes a bridge 109 feet 4 inches wide. Plans remain subject to design development and environmental review.
- Two travel lanes in each direction, separated by a raised median 5 feet 10 inches wide
- A 12-foot two-way bike lane on each side, with a concrete barrier on the north side
- Sidewalks of 13 feet 7½ inches on the north side and 17 feet 7½ inches on the south side
- Wider trails under the bridge and stabilized creek banks
- More space and structural support for the Zilker Eagle mini train
- Structural elements designed to echo the original bridge
- No large-load posting
The eastbound side shows a lane labeled "travel and right-turn." Everything else that Barton Hills drivers would want to know about the intersection is still blank.
The Azie Morton part of the plan is still open
The project officially includes improvements to the Barton Springs Road and Azie Morton Drive intersection. The 2023 council document names the underlying problem. The roadway west of Azie Morton does not line up with the roadway east of it. The project page has not published a final layout, signal plan or turn-lane design for that corner.
Construction staging is in a similar place. In 2023 the City described closing one lane at a time so people could keep using the intersection. The Austin Monitor reported that this mattered most for drivers coming from Azie Morton, "an outlet for drivers in the Barton Hills and Kinney neighborhoods." The council action that year promised only that "at a minimum the bridge will remain open to all modes of transportation during construction." City staff also said they want the bridge open for Zilker's big events, including the Trail of Lights, Austin City Limits Music Festival and Blues on the Green. The project FAQ now says temporary traffic and access impacts are expected, that phasing is still being evaluated, and that detour and lane-closure details will be posted as they become available.
So the corner Barton Hills uses every day is the part of the plan with the fewest commitments.
The calendar that actually decides it
The City's posted schedule, which it says may change, runs like this:
- Monday, November 16, 2026, 5 to 7 p.m. Community open house at Dougherty Arts Center, 1110 Barton Springs Road, with staff from the City, TxDOT and partner departments. The City notes it is not the formal NEPA public hearing.
- Date to be announced. A public comment period and the formal NEPA hearing, with details to be posted once confirmed.
- August to October 2027. Hearings and approvals under Chapter 26 of the Texas Parks and Wildlife Code, which covers proposed uses of dedicated parkland. These dates are targets and not yet confirmed.
- Late 2027. Anticipated NEPA decision.
- Late 2028. Expected start of construction.
The City now lists a construction start of late 2028. In June, the projection was summer 2027, with bid and award in late 2026 to early 2027, as Community Impact reported.
The open house is a chance to ask the City, TxDOT and partner departments about the Azie Morton turn lane, the misaligned roadway and how traffic will be staged. For anyone who prefers to write, the project team takes questions at [email protected] or 512-974-2300, and the project page has a sign-up for updates.
At Ace Team ATX, we keep track of what happens to the roads Barton Hills uses every day, and this bridge is one of the biggest. If you'd like to talk through how the project timeline lines up with your own plans to stay, sell or buy nearby, we're glad to help, in English or Spanish. Let's find your Austin home.