The Tract 110 Vote Isn't About Traffic Anymore. It's About a Signature From 2011.

The Tract 110 Vote Isn't About Traffic Anymore. It's About a Signature From 2011.

"I live at the intersection of Dahlgreen and Galsworthy, directly adjacent to the proposed secondary access point for this development. I've lived there for over five years, and I am asking this committee to postpone this case."

That's Alicia Keswani, testifying before Austin's Zoning and Platting Commission back in May. Her house sits at the exact corner where a 1,000-unit apartment project wants to put a driveway. If you live in Circle C, you've probably heard some version of her argument all summer, at HOA meetings, on neighborhood email threads, maybe at your own front gate. The story everyone tells is about traffic: too many cars, too close to Kiker Elementary, too little study.

That story isn't wrong. But it's not actually what's going to decide Thursday's vote.

What the City Council is voting on

The property in question is Tract 110, a roughly 67-acre parcel Stratus Properties owns at 11010½ South MoPac Expressway, tucked into the corner where MoPac meets Highway 45. Under the 2002 Circle C Development Agreement, that land is zoned for up to 650,000 square feet of commercial office space. Stratus wants to convert most of that entitlement into up to 1,000 multifamily apartment units, plus some retail and neighborhood commercial space.

The Zoning and Platting Commission already weighed in. On May 5, commissioners voted 8-0 to forward a revised recommendation to the full City Council, one that caps the unit count at 1,000, limits retail to 10,000 square feet, restricts impervious cover to 16.38 acres, and adds a list of prohibited uses like auto sales and pawn shops. That recommendation has been sitting in front of the Austin City Council since spring. A vote scheduled for July 23 got postponed. It's now set for this Thursday, September 10, at Austin City Hall.

District 8 Councilmember Paige Ellis, who represents Circle C, has said publicly that she hasn't taken a position on the case. She's on record supporting the delay specifically to gather more traffic data, and she met in June with representatives from the Protect Circle C Coalition, city transportation engineers, and environmental experts to work through the concerns.

The traffic numbers everyone's actually arguing about

City staff's own estimate puts the project at roughly 4,676 daily vehicle trips, including 424 trips during the morning peak hour and 386 in the evening peak. Those hours line up almost exactly with drop-off and pickup at Kiker Elementary, which sits within a quarter mile of the site. The Protect Circle C Coalition, a resident-run nonprofit that's been tracking the case since it was filed, argues that number is a significant undercount and has asked the city for a full Traffic Impact Analysis before any vote, not after.

The flashpoint is a single proposed access point on Dahlgreen Avenue, a two-lane residential street that also happens to be the road Kiker families use to walk, bike, and drive their kids to school. Stratus's original site plan put the main entrance off MoPac and treated Dahlgreen as emergency-access only. According to public statements from Councilmember Ellis, it was the city, not the developer, that later required a second access point, a requirement that would have applied even under the existing office zoning. That detail rarely makes it into the neighborhood conversation, but it matters, because it means the fight over Dahlgreen isn't purely a fight over what Stratus wants. It's also a fight over what the city's own access rules require of any project on that corner.

Why the traffic argument was never going to be the whole story

Here's the part that hasn't gotten much attention outside the actual case file. Dahlgreen Avenue access isn't just something residents don't want. It's something that's already supposed to be prohibited, twice over.

City Ordinance No. 020801-31, adopted in August 2002 as part of the original Circle C zoning, explicitly bars vehicular access from this tract to Dahlgreen Avenue. Separately, in September 2011, the Circle C HOA and Stratus entered into an Amended and Restated Declaration of Restrictive Covenants that repeats the same prohibition. Two independent legal protections, one municipal and one private, both saying the same thing: no cars from this tract onto Dahlgreen.

Stratus's current application asks the city to remove both. And that's where the story shifts from a traffic argument to a paperwork argument. According to filings submitted to the Zoning and Platting Commission in August, Circle C residents are now challenging the validity of the 2011 covenant amendment itself, on the basis that it may have been filed without proper authorization. If that challenge holds up, the legal foundation Stratus is relying on to reopen Dahlgreen access may not exist in the form the application assumes, regardless of what the City Council decides this week.

Layered on top of that is something most residents outside the coalition's core group probably don't know is happening. The Circle C HOA has negotiated a second amendment to the covenant, one that would formally clear the way for Dahlgreen access, but it isn't in effect yet. It's sitting in an escrow account managed by Heritage Title, and by the terms of that arrangement, it only gets filed if Stratus receives full zoning approval from the City Council on all three required readings. If that approval doesn't happen within two years, the escrowed amendment is voided and destroyed. In other words, the HOA board has already structured a private contingency deal around the outcome of a public vote that hasn't happened yet, and that deal is what actually determines whether Dahlgreen access becomes real, not the emotional testimony at City Hall.

A timeline, if you've lost track

Date What happened
August 2002 City ordinance bars vehicular access from Tract 110 to Dahlgreen Avenue
September 9, 2011 Circle C HOA and Stratus sign a restrictive covenant repeating the Dahlgreen prohibition
April 21, 2026 Zoning and Platting Commission postpones the case to May 5 at the neighborhood's request
May 5, 2026 Commission votes 8-0 to forward a revised recommendation, capped at 1,000 units
July 13, 2026 Stratus amends the application, expanding the tract boundary slightly to 67.432 acres
July 23, 2026 Original City Council vote date, postponed
August 18, 2026 Residents formally challenge the authorization of the 2011 covenant amendment
September 10, 2026 Rescheduled City Council vote

What this actually means if you live here right now

None of this means the apartments are or aren't getting built. It means the outcome depends on two separate processes running at the same time, one public and one private, and most of the coverage this summer has only told you about the public one.

If the Council approves the rezoning Thursday, that doesn't automatically open Dahlgreen. The HOA's escrowed second amendment still has to get filed, and the covenant-authorization dispute still has to get resolved, potentially in a courtroom rather than a council chamber. If the Council denies or further delays the case, the underlying question of whether the 2011 amendment was validly executed in the first place doesn't go away either. Either way, the traffic study argument that's dominated public comment for months is really a proxy fight for a legal question about a piece of paper from fifteen years ago.

For everyday life in the neighborhood this week, that means paying attention to two different things. Watch what the Council does Thursday, but also watch what happens with the covenant challenge, because that's the piece that determines whether a council approval actually translates into cars on Dahlgreen or gets tied up for another year. The Protect Circle C Coalition has been the most reliable source for tracking both threads as they move, and the city's own case file for C14-2025-0064 is public if you want to read the staff reports and commission minutes yourself.

Whatever happens Thursday, it's worth remembering that Circle C's character was built on exactly this kind of long, slow negotiation between growth and the neighborhood's own rules. This isn't the first time a piece of paper from decades past has ended up deciding what gets built at the edges of this community, and it won't be the last.

If you're a longtime Circle C neighbor trying to figure out what any of this means for your own street, your commute, or your home's value down the line, that's the kind of on-the-ground context Ace Team ATX tracks closely. Reach out any time you want a straight answer about what's actually happening in this neighborhood, not just what's trending on Nextdoor.

Work With David

By intently listening to his clients' needs, he goes above and beyond their expectations in helping them achieve their unique real estate goals. As a result, many of his clients become long-term friends.

Follow Me on Instagram